Due diligence of Ronchi hydropower plant
The project
With the aim of providing the client with all the elements to evaluate the potential acquisition of Ronchi hydropower plant, FROSIO NEXT carried out the due diligence of the plant.
In particular, FROSIO NEXT pefromed the following activities:
Technical part:
- Analysis of the available technical documentation provided by the client
- Visit to the plant
- Analysis of the reliability and completeness of the technical input data (hydrology, geology, topography)
- Analysis of the production and of the annual electricity generation
- Identification of the main technical-executive issues
- Evaluation of the potential improvements and relative costs
- Analysis of the operating costs
Administrative part:
- Analysis of the technical and administrative documentation
- Analysis of water concession, the analysis of the authorization path and of the PPA.
- Analysis of the decrees and of the PPA
- Analysis of the general authorization documentation
PROJECT’S FEATURES
DURATION
2020
LOCATION
Cuneo (CN), Italy
CLIENT
Idroelettriche Riunite SpA
ASSIGNMENT
Due Diligence
NAME OF THE PLANT
Ronchi hydropower plant
MAIN DATA OF THE PLANT
INSTALLED CAPACITY
0.336 MW
NOMINAL HEAD
39 m
MAXIMUM DISCHARGE
1,9 m3/s
Our projects
Contact us
Do you want to start a great project with us?
Fill the form and get in touch with us.